There has been so many ongoing projects along roadside like laying of cables along Juja Rd. This is a trend that is most likely to continue with advancement in technology.
Below is a check list from http://www.kenha.co.ke/index.php?option=com_jdownloads&Itemid=148&view=viewdownload&catid=15&cid=20

Checklist/Requirements for Roadside Developments
1. Application to construct or improve access roads to Class A, B, or C roads
• Application letter detailing the proposed developments and justification.
• A survey of the property from the Survey of Kenya
• Detailed Engineering Design Drawings with general layout, cross-sections and all other relevant details to scale (2 copies).
• A geo-referenced map (UTM map projection, Arc 1960 Datum) giving location and affected plot(s) in relation to the road (2 printouts and soft copy (CAD)).
• Complete application copied to Regional Manager of respective region for comments/consent following a site visit. Alternatively a site visit report from an officer from HQ.

2. Application to lay communication cables along and/or across class A, B or C roads
• Application letter detailing the proposed developments and justification.
• Detailed Engineering Design LayoutDrawings overlain on a properly geo-referenced map (UTM map projection, Arc 1960 Datum)showing cadastral data, longitudinal profile, cross-sections of typical trenches and road crossings (micro-tunneling), junctions and manholes/handholes with coordinates and all other relevant details to scale.Coordinates (X, Y) list for all the utility line bends and manholes/handholes should also be included in the map. Layout drawings should be provided for a scale of 1:2500 for the general layout and 1:500 for the details (crossings) and provided in 2 printed copies and in soft (CAD).
• Where service ducts are provided, the applicant shall not be allowed to lay the cable at any other point.
• Copied to Regional Manager of respective region for comments/consent following a site visit. Alternatively a site visit report from an officer from HQ.

3. Application to lay water pipelines along and/or across class A, B or C roads
• Application letter detailing the proposed developments and justification.
• Detailed Engineering Design Drawings overlain on properly geo-referenced maps (UTM map projection, Arc 1960 Datum)showing pipeline network and pipeline size(s), layout and profiles in relation to road, cross-sections of typical trenches and road crossings(reinstatement details where applicable), details of river crossings, road over rail/river bridge crossings & anchorages and all other relevant details to scale. Coordinates (X, Y) list for all the utility line bends and manholes should also be included in the map. Layout drawings should be provided for a scale of 1:2500 for the general layout and 1:500 for the details (2 printed copied & soft copy(CAD)).
• Where appropriate service ducts are provided, the applicant shall not be allowed to lay the pipe at any other point.
• Copied to Regional Manager of respective region for comments/consent following a site visit. Alternatively a site visit report from an officer from HQ.

4. Application to lay sewer lines along and/or across class A, B or C roads
• Application letter detailing the proposed developments and justification.
• Detailed Engineering Design Drawings overlain on properly geo-referenced maps (UTM map projection, Arc 1960 Datum) showing pipeline network and size(s), layout and profiles in relation to road, cross-sections of typical trenches and road crossings(reinstatement details where applicable) and all other relevant details to scale. Coordinates (X, Y) list for all the utility line bends and manholes should also be included in the map. Layout drawings should be provided for a scale of 1:2500 for the general layout and 1:500 for the details (2 printed copied & soft copy (CAD)).
• Copied to Regional Manager of respective region for comments/consent following a site visit. Alternatively a site visit report from an officer from HQ.

5. Application to erect power lines along and/or across class A, B or C roads and,
• Application letter detailing the proposed developments and justification.
• For underground cables, Detailed Engineering Design Drawings overlain on properly geo-referenced maps(UTM map projection, Arc 1960 Datum) detailing cable size(s), layout in relation to road, cross-sections of typical trenches and road crossings(micro-tunneling), road over rail/river bridge crossings & anchorages and all other relevant details to scale. Coordinates (X, Y) list for all the utility line bends and manholes should also be included in the map. Layout drawings should be provided for a scale of 1:2500 for the general layout and 1:500 for the details (2 printed copied & soft copy(CAD)).
• For overhead cables, detailed Engineering Design layout drawing showing the cable route and the position of all poles overlain on a properly geo-referenced map.
• Copied to Regional Manager of respective region for comments/consent following a site visit. Alternatively a site visit report from an officer from HQ.

6. Application to install any form of advertisement on road reserves along class A, B or C roads
• Application letter detailing the proposed developments and justification.
• A properly geo-referenced location map (UTM map projection, Arc 1960 Datum) showing all salient features and the location of the advertisement structure (with coordinates) in relation to the road and other existing utilities. Maps should be provided for a scale of 1:2500 for the general layout and 1:500 for the details (2 printed copied & soft copies(CAD)).
• For the support structure, detailed Engineering Design Drawing and supporting computations certified by a Registered Structural Engineer (2 copies).
• Copied to Regional Manager of respective region for comments/consent following a site visit. Alternatively a site visit report from an officer from HQ.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s